Construction Quotation and Progress Claim

Price your bill of quantities, then claim progress with retention and advance recovery worked out.

Bill of quantities (BOQ)
%
%

The overhead and profit rates are an example; enter the rates for your project.

How was this calculated?

A construction quotation, the financial offer, starts from the bill of quantities: each work item with its quantity and unit cost, plus overheads, supervision and profit, which give the unit rate you offer the employer. Once the contract is signed, the same bill becomes a periodic progress claim (payment application) that measures how much of each item is done. Enter the items in the "Construction quotation" tab, then switch to "Progress claim" and type the progress, and the generator works out work done to date, this claim, retention, advance payment recovery, Saudi VAT and the net amount due. The Excel download keeps live formulas so you can carry on with the next claims.

Short answerThis claim = value of work done to date − work certified in earlier claims. Retention and advance payment recovery come off that amount and VAT is added, which leaves the net paid to the contractor.

How the generator prices the quotation and the progress claim

The unit rate in the quotation is the item's direct cost (materials, labour and plant) plus the overhead percentage, then the profit percentage on top of that. Each item's amount is its quantity times its unit rate, and the items add up to the contract value before VAT. In the claim, each item's value is multiplied by its progress to date, and whatever was certified in earlier claims is subtracted.

Unit price = Cost × (1 + OH) × (1 + Profit) · Net = Current − Retention − Advance recovery + VAT

Example 1, quotation for a villa structure (illustrative): excavation and backfill 450 m³ at a cost of 20, concrete 120 m³ at 600, blockwork 900 m² at 50 and plaster 1,800 m² at 25. Direct cost is SAR 171,000.00. With 10% overheads and 10% profit, a cubic metre of concrete is priced at 726.00, the contract value is 206,910.00, VAT is 31,036.50 and the total is SAR 237,946.50.
Example 2, the first claim: excavation is complete, concrete is 60% done and blockwork 25%. The work is worth 76,774.50 with nothing claimed before. Retention at 10% is 7,677.45, advance recovery at 10% is 7,677.45, VAT on 69,097.05 is 10,364.56, so the net due is SAR 71,784.16 and overall progress is 37.1%. The "Example: villa structure" button loads this case.
Example 3, the second claim: after "Set up the next claim", the first claim's percentages become the previous ones. Concrete is now complete, blockwork 70% and plaster 40%: work to date is 157,905.00, previous claims 76,774.50, so this claim is 81,130.50, retention 8,113.05, recovery 8,113.05, VAT 10,952.62 and the net SAR 75,857.02.

Construction quotation format

A construction quotation is laid out as a bill of quantities: item number, description of the work with its specification, unit of measurement (m³, m², linear metre, lump sum), quantity, unit rate and amount. Employers compare tenders by unit rate rather than by the total alone, because quantities change on site and the contractor is paid for the quantities actually built. That is why overheads and profit do not sit on a separate line in the quotation you send; the generator spreads them over each unit rate and keeps the breakdown for you in the Excel file.

The quotation should also state the construction period, how long the offer stays valid, what the price excludes (temporary power connection, permit fees), the proposed advance payment and retention rates, and whether prices include VAT. You can download the quotation in Word to add your covering letter and your company letterhead.

Estimating the cost of a construction project

The direct cost of an item is what it takes to build one unit: materials including wastage, labour wages and equipment hire. Overheads are costs that belong to no single item: the site engineer's and supervisor's salaries, accommodation and transport, insurance and bank guarantees. Under the table, the generator shows direct cost, overheads and profit on separate lines, so you can see how much of the contract value you keep.

ComponentExamplesHow it enters the price
MaterialsReady-mix concrete, rebar, blocks, cementDirect unit cost
LabourCarpenters, steel fixers, masonsDirect unit cost
PlantConcrete pump, excavator, scaffoldingDirect unit cost
Overheads and supervisionSite engineer, accommodation, insurance, guaranteesPercentage of direct cost
ProfitThe contractor's marginPercentage of cost after overheads

Progress claim template in Excel

A progress claim, also called a payment application or interim payment certificate request, is the contractor's periodic request for the value of work done since the last claim; the supervising engineer checks it before the employer approves it. The "Progress claim" tab exports an Excel sheet showing, for every item, the quantity, unit rate, previous progress, progress to date, previous value and this claim's value, followed by retention, recovery and VAT as formulas. For the next claim, copy the "to date" column into "previous" and type the new percentages.

  • Retention: a percentage held back from every claim as security for defects, released at provisional or final handover depending on the contract. The generator totals it under the table so you know your retention balance.
  • Advance payment recovery: the advance paid at signing is recovered by deducting a percentage from each claim until it is repaid. The generator uses the advance percentage by default and stops once the advance is fully recovered; you can change the rate under "Full details".
  • Performance bond: a bank guarantee the contractor provides at signing. It is separate from cash retention and is not deducted from claims.

VAT on progress claims and construction invoices

In Saudi Arabia, VAT on a claim is calculated on the value of work done in that claim, not on the net after retention, because retention is part of the work's value with payment deferred. If a tax invoice was issued for the advance payment when it was received, the advance recovery is deducted from the claim's VAT base so that VAT is not charged twice on the same amount. The generator assumes this and lets you switch it off; for the treatment of a specific contract, refer to the implementing regulations of the VAT law. The approved claim is the basis for the contractor's tax invoice; it does not replace it.

Technical and financial proposals for tenders

A tender usually asks for two envelopes: a technical proposal evaluated first, and a financial proposal opened only for bidders who qualify technically. Government tenders in the Kingdom are published on the Etimad platform. The financial proposal is the priced bill of quantities this generator produces. The contractor writes the technical proposal, which normally covers:

  1. Understanding of the scope and the method statement for each stage.
  2. The programme and key milestones.
  3. The proposed technical team with their CVs.
  4. Plant and equipment available for the project.
  5. Similar past projects and their completion certificates.
  6. The quality and site safety plan.

Do not put any price in the technical proposal; many tender documents disqualify a bid that reveals its price in the technical envelope.

Common mistakes in progress claims

  • Entering progress for this period instead of progress to date, so the current work is counted twice or lost.
  • Calculating VAT on the net after retention, which understates VAT on the work done.
  • Carrying on deducting advance recovery after the advance has been repaid.
  • Progress to date lower than the previous claim without a variation order to justify it.
  • Adding new items to a claim without an approved variation order setting their price.
  • Not keeping a running retention balance, which makes it hard to claim back at handover.

What to do after preparing the claim

Download the claim as a PDF and attach the evidence for the quantities: measurement sheets, inspection and acceptance records and site photos, then submit it to the supervising engineer. Once it is approved, issue the tax invoice for its value. For the next claim, press "Set up the next claim" so the to-date percentages move to "previous" and the claim number goes up, or download it to Excel and continue there. "Share as link" opens the generator with the quotation data for a colleague to review.

When claims are spread across several projects

One claim on one project fits in a spreadsheet. Once you run several projects, each with its own contract, advance, retention, material purchases and labour costs, it gets hard to see the profit on each project and what each owner still owes you. At Microtec we offer contractors across Saudi Arabia accounting software (ERP) that brings sales, purchasing, inventory, finance and HR into one system. Try it on the projects you are running now.

Frequently asked questions

What is a progress claim in construction?

A periodic request by the contractor for the value of work done since the previous claim, based on the progress of each item in the bill of quantities. Retention and advance recovery are deducted, then the supervising engineer and the employer approve it.

How do I calculate the value of the current claim?

Multiply each item's value by its progress to date, add the items up, then subtract everything certified in earlier claims. The result is the value of work in this claim, and deductions and VAT are worked out from it.

What is the usual retention percentage in construction contracts?

The contract sets it, and ten percent is common in many Saudi contracts. Retention is deducted from every claim and released at provisional or final handover, or replaced by a bank guarantee if the contract allows.

How is the advance payment recovered from progress claims?

By deducting a percentage of each claim's work value, often the same percentage as the advance, until the total recovered equals the advance. Deductions then stop; the generator stops at full recovery and shows what remains.

Is VAT on a progress claim calculated before or after retention?

Before retention, because retention is part of the value of work done with payment deferred. Advance recovery is taken off the VAT base if the advance was invoiced with VAT when it was received.

How do I write a construction quotation?

Prepare a bill of quantities with each item's unit, quantity and unit cost, add overheads and profit to the unit rate, then state the construction period, validity and payment terms. The generator prices the items and exports them to Word, PDF or Excel.

↑